30 Health Centres Operational, 230 Completed And 100 Equiped - Enugu SSG

 Enugu: 260 Type 2 Primary Health Centres Cost About N90 Million Per Unit - Onyia


Enugu: 260 Type 2 Primary Health Centres Cost About N90 Million Per Unit - Onyia


The unit cost of a Type 2 Primary Health Centre is N90 million, covering the building, equipment, solar power system, staff accommodation, and perimeter fencing. The total project cost is about N24… pic.twitter.com/COX1v3C1Lz


— ARISE NEWS (@ARISEtv) April 24, 2026



The unit cost of a Type 2 Primary Health Centre is N90 million, covering the building, equipment, solar power system, staff accommodation, and perimeter fencing. The total project cost is about N24 billion. Currently, 30 centres have been completed and are operational. Construction of the remaining 230 is complete, and the Enugu State Governor has approved the equipping of 100 units.


Prof. Chidiebere Onyia

Secretary to the State Government, Enugu State